Buckhurst Embankment Retention
Client: AM1
Location: Buckhurst
Overview
PACE Infrastructure Solutions Ltd was appointed to deliver emergency design and build
bank
stabilisation works at Buckhurst in the Wessex region. The intervention followed the
identification of a significant embankment slip risk during planned high-voltage (HV)
upgrade works. With tight timescales, evolving access constraints, and complex site
conditions, PACE responded rapidly to deliver a bespoke stabilisation solution that
addressed both safety and operational concerns.
Our Scope
PACE’s full-scope service included:
- Design and implementation of cost-effective retention systems to stabilise the embankment
- Protection and management of existing buried HV infrastructure adjacent to the works
- Adaptation to access restrictions, including reactive planning following the loss of a
planned level crossing access point
- Use of mobile crane logistics to deploy and remove plant due to last-minute road closures
- Delivery of all works within a 52-hour blockade
- The project required high levels of flexibility, coordination, and technical precision to
ensure successful execution.
Technical Approach
To meet the urgent nature of the works, PACE deployed a collaborative and agile approach:
- Early Contractor Involvement: Immediate engagement with the client ensured alignment on
technical solutions and delivery plans
- Cost-effective Design: Retention methods were carefully selected to meet site-specific
constraints and budgetary requirements
- Access and Methodology Adaptation: Following a loss of planned access just one week prior to
delivery, the team rapidly transitioned to a mobile crane solution
- Hydrostatic Pressure Management: Jet water filters were incorporated to relieve pressure
behind the retention structure, enhancing long-term stability
Outcome
PACE completed the Buckhurst bank stabilisation project within the allocated 52-hour blockade
and budget, with no additional possessions required. The successful delivery resulted in:
Zero delays to the HV upgrade programme
Significant cost efficiencies through proactive planning and solution-led engineering
Client satisfaction, with the works meeting all expectations under high-pressure conditions
This project highlighted PACE’s ability to deliver reactive, high-quality infrastructure
solutions in logistically complex and safety-critical environments.